The José Cabrera nuclear power plant is located in the municipality of Almonacid de Zorita, in Guadalajara, and it was the first nuclear power plant to begin operation in Spain, in 1968. After 38 years of operation, it was shut down by Ministerial Order on 20 April 2006. This entailed the first full dismantling of a nuclear power plant in Spain.
Timeline
Enresa submits the Basic Strategy Analysis for the dismantling of the plant.
Enresa submits the preliminary Dismantling Plan to the Nuclear Safety Council.
The Ministry of Industry grants approval for shutdown on 20 April 2006.
Start of spent fuel management and pre-dismantling tasks.
Enresa applies for authorisation for dismantling.
Approval issued by the Nuclear Safety Council.
Loading of spent fuel casks and emplacement in the onsite interim storage facility.
1 February 2010: The Ministry of Industry, Tourism and Trade authorises the transfer of ownership from Gas Natural Fenosa to Enresa for the start of the dismantling phase.
Start of the dismantling of conventional components and disassembly of equipment and refitting of the turbine building.
Start of disassembly in radiological areas.
Start of underwater segmentation of the reactor internals.
Conditioning in the auxiliary building of the first cask with waste from the reactor.
Segmentation of the reactor internals is completed.
Start of disassembly of the steam generator.
Loading of four containers with special waste from the segmentation of the reactor internals and operational waste in the individual interim storage facility.
Start of the underwater cutting of the reactor vessel closure.
Start of the cutting of the reactor vessel.
Segmentation of the reactor vessel is completed.
Disassembly of the steam generator is completed.
Dismantling of components and systems from the radiological containment and auxiliary areas is completed.
Start of removal of radioactive concrete and decontamination of cavities.
Start of surface decontamination in the containment and auxiliary buildings.
Segmentation of reactor bioshield concrete.
Decontamination of buildings.
Installation and test of the soils clean-up facility.
Buildings Decontamination.
Buildings Decontamination.
Stack Demolition.
Final radiological disassemblies.
Buildings release, decontaminations, demolitions and excavations
Buildings release, decontaminations, demolitions and excavations.
Buildings release, decontaminations, demolitions and excavations.
Buildings release, decontaminations, demolitions and excavations. Restoration Plan
Restoration Plan
Preliminary Activities
The pre-dismantling activities, carried out between 2006 and 2009 under the responsibility of the facility’s operator, consisted mainly of the management of spent fuel and the conditioning of operational waste.
After the completion of the pre-dismantling activities and the corresponding ministerial authorisation of 11 February 2010, ownership of the José Cabrera nuclear power plant was transferred to Enresa for the implementation of the Dismantling and Decommissioning Plan.
Dismantling and Decommissioning Plan
Since its shutdown in 2006, Enresa began to draft the regulatory documentation for the Dismantling and Decommissioning Plan for the José Cabrera Nuclear Power Plant. The activities to be carried out during the project and their specifics were devised in parallel.
Enresa envisages dismantling projects as an industrial process aimed at the complete release of the site and the proper management of the resulting materials.
The tasks include: the removal of conventional elements; the disassembly of radiological components; decontamination and demolition of buildings; and environmental restoration of the site.
The Dismantling and Decommissioning Plan for the José Cabrera Nuclear Power Plant prioritises the safety of the workers involved and the protection of the general public and the environment.
All activities are subject to rigorous planning and strict controls, taking into account both the occupational risks common to any conventional industry and those which are radiation-specific.
Preparatory Activities
During the initial stage, between 2010 and 2011, it was necessary to adapt some of the plant’s systems and auxiliary facilities to make them available and functional for the activities involved in dismantling.
One of the most important actions was the disassembly of the original equipment and the subsequent transformation of the turbine building into the new Auxiliary Building for Dismantling, for the treatment and temporary storage of waste from the containment building.
Various actions were carried out to reduce risks and prevent interruption in the course of future work.

Move the controller to change
between before/after
Dismantling of Conventional Components
The plant’s conventional buildings and facilities were dismantled, since they were no longer required. To date, the elements and components from the following areas have been dismantled:
- Diesel building
- Cooling towers
- Electrical building and former control room
- Electrical transformer area
Dismantling of Radiological Components
Igualmente se ha procedido a desmontar in situ el resto de grandes componentes del circuito primario (generador de vapor, bomba principal y presionador ). En paralelo se han retirado los equipos y sistemas radiológicos en desuso de los diferentes locales de los edificios de Contención y Auxiliar.
Decontamination and Demolition of Buildings
Management of Materials
Site Restoration
In order to restore the site to its initial state, the Restoration Plan will ensure that the land to be released is free of residual radioactivity. During this final phase, site clean-up and final characterisation will be carried out before application is made for the declaration of decommissioning, with the aim of returning the site to its owner.

Move the controller to change
between before/after